wiki:IIRS/DevelopmentPlan

Version 27 (modified by jim, 3 years ago) (diff)

--

Development plan

Notes:

  • Time in [square brackets] is an estimate, (hours in normal brackets) on done items is time actually spent.
  • 21.5 hrs - early design meetings and documentation - already done

Alpha (19 September)

Delivers a D7 Panopoly-based site based on TN's own new distribution, with component/plugabble (initiative) widget system, internationalisation capabilities.

Progress

26 August -- 4 hours spent

  • Clone winacc_panpoly distribution repo -> rename to transitionnetwork_d7 - transitionnetwork_d7 repo (1.5 hours)
  • Change profile to be TN-focused, include key modules: (1 hours)
    • Address, Geofield, geocoder, geophp
    • Leaflet
    • dnl, i18n
  • Set up local development site (1.5 hours).

28 August -- 3h (7h total)

  • R&D into
    • various aspects: BOA, Leaflet/OpenLayers?, makefiles etc (0.5 hours)
    • R&D into internationalisation dnl, i18n (0.5 hours)
  • Create Initiative content type with required fields (0.5 hours)
  • Create Base and Initiative feature, push to GitHub? (1.5 hours) -- Base repo, Initiative repo

29 August -- 4h (+7h total)

  • Social login decided, added to makefile: HybridAuth? Social Login (0.5 hours)
  • R&D for user profile modules, added user profile2 module (0.5 hours)
  • Ed Mitchell & Jim Kirkpatrick Skype PM/Design/Progress meeting (1 hour)
  • Looked into: Countries, Location Taxonomize and decided to KISS for now. (0.25 hours)
  • R&D/Decision Made: NO user location-related fields present on basic Drupal account, First, Last & Middle name fields only. ALL location and other features for users will be on Profile2 and defined later. (0.25 hours)
  • Added realname and realname_registration to remove need for username on registration (0.25 hours)
  • Create User Profile feature (decide approach Profile2 vs core user fields etc) (0.75 hours) -- User repo
  • UNDERWAY Investigate I18n & related language/internationalisation modules & best practice -- see https://drupal.org/node/133977 (0.25 so far)
  • UNDERWAY Resolve tension/shortcoming in nested Drush Makefiles causing module dupes between /profiles/modules and /sites/all/modules - https://drupal.org/node/1006620 (0.25 so far)

Development total so far: 11 hours

To Do

  1. [3] R&D Add & set up Social media login/integration, convert basics to feature.
  2. [8] Begin/convert new Widget modules (core, initiative, registration etc) -- TO BREAK DOWN ONCE UNDEWAY
  3. [4] Debug & improve Hub install profile.
  4. [1] Set up test site on Jim's server
  5. [3] Create very simple Bootstrap-based theme (little/no customisations)
  6. [8] Begin/convert new Widget modules (core, initiative, registration etc) -- see
  7. [8] Enable French language and translate some key bits with Google Translate.
  8. [32] Convert D6 widget modules & features to D7 per IIRS/SolutionDesign
  9. [4] Create 'Hub Profile' on clone (STG?) of D6 TN.org containins basic text, country, language and widget displays.
  10. [8] (Ben?) Update widget HTML/CSS/theme as needed.
  11. [2] Add Services related modules as needed
  12. [8] Update all views, panels, features to handle language context.

Expected total: 12.25 +/- 5 (= 98 - 140 hrs)

Beta (? October)

Delivers a cleaned/tweaked up system and some web services connections back to the D6 site, plus an installed and integrated beta website.

  1. [12] Fix bugs/do tweaks
  2. [32] Add Services to sync between D6 <--> D7 sites (and future hub sites) with resilient queuing, plugable architecture
  3. [12] Test, tweak, prep Beta, install, integrate

Subtotal: 6.5 +/- 3 days (= 52 - 76 hrs)

Total: 18.75 +/- 8 days (= 150 - 216 hrs)

NB: from Ed - Jim - your total time budget is 150 hrs. This gives us 3 days with a second programmer in beta phase (agreed as good idea). Bear this in mind!