wiki:IIRS/DevelopmentPlan

Version 8 (modified by jim, 3 years ago) (diff)

--

Development plan

Note time in [square brackets] is an estimate, (hours in normal brackets) on done items is time actually spent.

  • 17.5 hrs - early design meetings and documentation - already done

Alpha (19 September)

Delivers a D7 Panopoly-based site based on TN's own new distribution, with component/plugabble (initiative) widget system, internationalisation capabilities.

Done

  1. 0.25 Clone winacc_panpoly distribution repo -> rename to transitionnetwork_d7 (1.5 hours) - Distro here: https://github.com/transitionnetwork/transitionnetwork_d7
  2. 1.0 Change profile to be TN-focused, include key modules: (0.5 hours)
    • Address
    • Geofield, geocoder, geophp
    • Leaflet
  3. Set up local development site (1.5 hours).
  4. R&D into various aspects: BOA, Leaflet/OpenLayers?, makefiles etc (0.5 hours)

Development total so far: 4 hours

To Do

  1. [1] Set up test site on Jim's server
  2. [12] Change profile and extend Distro to be TN Hub focused, needs extra key modules including:
    • User profile-related modules
    • Social media login/integration
    • Services modules
  1. [0] Look at Debut feature and include where sensible Not needed at present
  2. [4] Create Initiative feature
  3. [2] Investigate I18n & related language/internationalisation modules & best practice
  1. [4] Create User Profile feature (decide approach Profile2 vs core)
  2. [4] Create very simple Bootstrap-based theme (little/no customisations)
  3. [8] Begin/convert new Widget modules (core, initiative, registration etc) -- see
  4. [8] Enable French language and translate some key bits with Google Translate.
  5. [32] Convert D6 widget modules & features to D7 per IIRS/SolutionDesign
  6. [8] (Ben?) Update widget HTML/CSS/theme as needed.
  7. [8] Update all views, panels, features to handle language context.

Expected total: 12.25 +/- 5 (= 98 - 140 hrs)

Beta (? October)

  1. [12] Fix bugs/do tweaks
  2. [32] Add Services to sync between D6 <--> D7 sites (and future hub sites) with resilient queuing, plugable architecture
  3. [12] Test, tweak, prep Beta, install, integrate

Subtotal: 6.5 +/- 3 days (= 52 - 76 hrs)

Total: 18.75 +/- 8 days (= 150 - 216 hrs)

NB: from Ed - Jim - your total time budget is 150 hrs. This gives us 3 days with a second programmer in beta phase (agreed as good idea). Bear this in mind!