    140140== EM additions to JK estimates == 
    141141* Phase 3.1 
    142  * Development estimate: 20-25 days 
    143  * Theming: 5 days 
    144  * Usability: 3-5 days 
     142 * Development estimate: 25-30 days 
     143 * Theming: 5-10 days 
     144 * Usability: 5 days 
    145145 * Project management, production, testing, editorial: 2 days per week (Ed so cost in core)  
    146 * ''' ED TOTAL: range = 35-40 days. ''' 
     146* ''' ED TOTAL: range = 40-45 days. ''' 
     147* ''' ED financial: 40 days, 320 hours, av rate £38 p/h = £12,160 -- 45 days, 360 hours, av rate £13,680) 