146 | | * ''' ED TOTAL: range = 40-45 days. ''' |
147 | | * ''' ED financial: 40 days, 320 hours, av rate £38 p/h = £12,160 -- 45 days, 360 hours, av rate £13,680) |
| 146 | * Ed total: range = 40-45 days |
| 147 | * Ed financial: 40 days, 320 hours, av rate £38 p/h = £12,160 -- 45 days, 360 hours, av rate £13,680) |
153 | | * ''' ED TOTAL: range = 26-35 days. ''' |
154 | | * ''' ED financial: 26 days, 208 hours, av rate £38 p/h = £7,904 -- 35 days, 280 hours, av rate £38 p/h = £10,604) |
| 153 | * Ed total: range = 26-35 days. ''' |
| 154 | * Ed financial: 26 days, 208 hours, av rate £38 p/h = £7,904 -- 35 days, 280 hours, av rate £38 p/h = £10,604) |
160 | | * ''' ED TOTAL: range = 25-40 days. ''' |
161 | | * ''' ED financial: 25 days, 200 hours, av rate £38 p/h = £7,600 -- 40 days, 320 hours, av rate £38 p/h = £12,160) |
162 | | * Project management overhead |
| 160 | * Ed total: range = 25-40 days. |
| 161 | * Ed financial: 25 days, 200 hours, av rate £38 p/h = £7,600 -- 40 days, 320 hours, av rate £38 p/h = £12,160) |
| 162 | * Project management overhead for each phase: Add this to all of them |
165 | | * Documentation: getting techs to write stuff up (AKA pulling teeth): (1 hr p/w for 12 weeks per tech) x 2 techs, = 12x2x38 = £912 per phase |
166 | | * ''' ESTIMATE per phase project management costs for techs: £5,00 per phase |
167 | | * Phases totals combining tech and project costs |
| 165 | * Documentation: getting techs to write stuff up (AKA pulling teeth from chickens): (1 hr p/w for 12 weeks per tech) x 2 techs, = 12x2x38 = £912 per phase |
| 166 | * Total estimated project management costs for techs: £5,00 per phase |
| 167 | * ''' Phases estimated totals combining tech and project costs ''' |