    2222=== Process for Phase 1: TNv3.1 === 
    23 ''JK time estimates added in italics'' 
     23''JK development time estimates added in italics'' 
    2424 
    25251. Autumn 2013: Prune and prepare 
     
    4848 * Measure 
    4949 
    50 ==== JK estimates for Phase 3.1 ==== 
     50==== JK development estimates for Phase 3.1 ==== 
    5151* Parts 1-3 (prune/design/plan) = 3 days 
    5252* Part 4 - Build - breakdown: 
     
    106106 * integrate with TN diagnostic tool and process - Tis complete easy tool to assess  
    107107 
    108 ==== JK estimates for Phase 3.2 ==== 
     108==== JK development estimates for Phase 3.2 ==== 
    109109 
    110110* Choose and implement advanced user engagement, commenting, voting and gamification (rewards/badges etc). ''2-5 days'' 
     
    123123 * integrate with a CRM package  
    124124 
    125 ==== JK estimates for Phase 3.2 ==== 
     125==== JK development estimates for Phase 3.2 ==== 
    126126* Democratisation/internationalisation of above CRM & knowledge featureset (i.e. make available to the world where needed) ''2-4 days'' 
    127127* Build and enhance Projects offering. ''1-2 days'' 
     
    132132* '''Total Phase 3.3 = 11-23 days''', likely to be below midpoint of this (17) as much is unknown at this point. '''Gut says 12-18 days.''' 
    133133 
    134 == JK Estimates total == 
     134== JK development estimates total == 
    135135* Phase 3.1 = 14-33 days, gut says 15-20 days 
    136136* Phase 3.2 = 8-24 days, gut says 10-15 days