Changes between Version 32 and Version 33 of TransitionMaintenance


Ignore:
Timestamp:
12/16/13 16:46:32 (3 years ago)
Author:
ed
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • TransitionMaintenance

    v32 v33  
    66 
    77NB: Ed realised his maths is up the spout on 3/12 and that the monthly amount approved from the board meet was £6,000 + £3,250 = £9,250 = £770 per month. Ed has to edit the page and the timesheets for techs spreadsheet to reflet this. Ed thinks it boils back to his miscalculation for the board report in July but needs to assess...  
     8NB: 16/12: we have some extra budget to cover the maintenance up to £1,000 per month for December 2013 - March 2104 - Hurray!  
    89 
    9 £1,027.77 = approx 29.4 hours at an average (rounded up) rate of £35p/h  
     10£1,000 = approx 28 hours at an average (rounded down by not particularly scientifically so be careful) of £35p/h 
    1011 
    1112Most of this work will be around website hosting and maintenance, but there will be times when developers do stuff too.  
    1213 
    13 All work done for this needs to be on tickets categorised with the milestone maintenance, and the category maintenance. 
     14All work done for this needs to be on tickets categorised with the milestone maintenance; it is possible to have different categories (task, enhancement etc.) 
    1415 
    1516== Monthly process in detail == 
    1617 
    17 1. we have £1,027 per month for maintenance 
     181. we have £1,000 per month for maintenance 
    18192. *all* maintenance work that wants to be paid *has* to be logged in TRAC maintenance tickets 
    19 3. Ed runs mid-monthly reports to get a feel of how we're doing and let you all know 
    20 4. Ed runs end-month report to sum up a month and assess techs' times and related costs 
    21 5. Ed adds tech times to 'timesheets for techs' spreadsheet 
    22 6. Ed requests invoices for that month's work from relevant techs 
    23 7. Techs check invoice request and produce invoices which they send to Ed 
    24 8. Ed checks tech invoices, saves them, sends them onto Jo for payment cc-ed to Sally for book-keeping 
     203. Web ops runs mid-monthly reports to get a feel of how we're doing and let all ttechs know on ttech list 
     214. ASAP in a new month: Web ops runs end-month report from month before to sum up a month and assess techs' times and related costs 
     225. Web ops adds tech times to 'timesheets for techs' spreadsheet 
     236. Web ops assesses tech charges based on different techs' hourly rates 
     246. Web ops requests invoices for that month's work from relevant techs on ttech list 
     257. Techs check invoice request and produce invoices which they send to Web ops 
     268. Web ops checks ttech maintenance invoices, sets the timesheets spreadsheet to orange, saves a copy in business folder, sends them onto Jo for payment cc-ed to Sally for book-keeping (ref: Core budget, Web, maintenance) 
    25279. Any leftovers go into the general maintenance budget (can be used for agreed site enhancements) 
    26 10. Jo tells Ed when invoices have been paid 
    27 11. Ed updates techs and updates the timesheets for techs spreadsheet of payment 
    28 12. we aim to have quarterly maintenance skypes for all concerned 
     2810. Jo pays the invoices within two weeks if possible and tells Web ops when invoices have been paid 
     2911. Web ops updates techs and updates the timesheets for techs spreadsheet of payment by making it green 
     3012. There is a general aim to have quarterly maintenance skypes for all concerned 
    2931 
    3032 
     
    4143 * September 2013: 38.34 hrs: £1,367 to bill. 8.94 hrs over-time-budget, £339.23 over-cash-budget. But still 17.76 hrs under running total budget and £697.12. Big month; lots of drupal and server work to sort out performance issues. 
    4244 * October 2013: 33.57 hrs: £1,210.45 to bill. 4.17 hrs over-time-budget, £182.68 over-cash-budget. Still 13.6 hrs under running total budget and ££514.44; another big month but we're staying under the quarterly estimate owing to August's incredibly quiet month.  
    43  * November 2013: 14/11 report: 22.8 hrs: £777.56 to bill. 6.52 hours under-time-budget, £250.21 under-cash-budget. Calmer month. Good to get some cash under the belt; we're 'in the green' on the running total by approximately 19 hours/£740  
     45 * November 2013: 23.88 hrs: £808.81 to bill. 5.52 hours under-time-budget, £216-ish under-cash-budget. Calmer month. Good to get some cash under the belt; we're 'in the green' on the running total by approximately 19 hours/£700 
     46* December 2013: ... [month's total]: [£to bill]. ...  
    4447 
    4548== Changes made in July following board meeting and new budget and daily rate ==