    3737 * July 2013: 28.7 hrs: £900.69 billed. 0.7 hrs leftover, £127.08 in credit for the month. Another big month, and included 5 hrs of design time to patch up Transition Culture.  
    3838 * August 2013: 3.4 hrs: £118.50 billed. 26 hours leftover, £909.27 in credit for the month. 
    39  * September 2013: ...  
     39 * September 2013: 38.34 hrs: £1,367 to bill. 8.94 hrs over-time-budget, £339.23 over-cash-budget. But still 17.76 hrs under running total budget and £697.12. Big month; lots of drupal and server work to sort out performance issues. 
    4040 
    4141== Changes made in July following board meeting and new budget and daily rate ==